Asset-Backed Financing in Indonesia: How to Lend to a Pre-Revenue Manufacturer

· 6 min read · Nucky Poedjiardjo, Managing Partner

Asset-Backed Financing in Indonesia: How to Lend to a Pre-Revenue Manufacturer

Most lending in Indonesia is underwritten against cash flow. The borrower shows audited revenue, a debt-service ratio is calculated, and the security sits behind that as a second line of defence.

A newly built manufacturing facility breaks that model. The plant exists, the machinery is installed, the land title is clean, and there is no revenue yet, because the final licence has not been issued and production has not started. The assets are real. The track record belongs to the parent, not the borrower.

This situation is common in Indonesian industrial development, and it is consistently mispriced in both directions.

The security has to carry the whole case

When there is no operating history, asset coverage stops being a fallback and becomes the thesis. That changes what diligence has to establish.

A book value of, say, USD 23 million against a USD 15 million facility looks comfortable at first glance. It is not, until three things are tested:

  • What is actually securable. Land and building are mortgageable. Machinery may be, but perfection and enforcement differ, and installed plant can be hard to realise separately from the site.
  • What the valuation rests on. Book value is an accounting figure, often carried from construction cost. A fresh independent valuation is not a formality here. It is the number the entire credit depends on.
  • What the title permits. Rights to a given expiry date, the number of separate titles, any encumbrance already registered. Eight titles are eight sets of confirmations, not one.

Strip machinery out and compute LTV against land and building alone. If the facility only works when plant is included in the coverage, the structure is thinner than it appears.

Two structures, two different risks

Where a borrower is pre-revenue, the choice of instrument matters more than the coupon.

Senior secured term loan. Typically a six-year tenor with an interest-only grace period, commonly 24 months, then amortisation, secured by a first-ranking mortgage over land, building and machinery. The grace period is doing specific work: it bridges the gap between funding and first revenue. Get that period wrong and the first amortisation payment arrives before the production ramp has generated anything to pay it with.

Sale-and-leaseback with buy-back. The investor acquires the property outright at a discount to market value, leases it back to the operator on a long lease, and grants a buy-back right at an agreed price. The investor owns the asset rather than holding security over it, which removes enforcement risk entirely. There is nothing to foreclose on.

The trade-off is real on both sides. The operator surrenders ownership and pays rent through the ramp-up, which is a cash cost at the worst possible moment. The investor takes residual risk on whether the buy-back is exercised and whether the asset is re-lettable if it is not. A 25 percent discount to market on entry, with buy-back at market, prices that risk explicitly rather than burying it in a coupon.

Which one fits depends less on preference than on whether the lender can realistically enforce a mortgage over a single-purpose industrial site in a regional location. If enforcement is doubtful, ownership beats security.

Parent support is a document, not a relationship

Where the commercial record sits with the parent and the borrower is a new entity, the parent's involvement has to be written down. "Parent guarantee under discussion" and "parent guarantee executed" are different credits.

What matters: whether the guarantee is of payment or of collection, which obligations it covers, whether it survives a change of control at the parent, whether the guarantor is in a jurisdiction where a judgment can be enforced, and whether the guarantor has the financial capacity to perform. A guarantee from an entity that cannot be reached is a comfort letter with a better name.

Licensing is a condition, not a detail

Where final operating licences are pending, the funding sequence has to reflect it. A licence expected imminently is still a licence not yet issued, and in Indonesia timelines move.

The practical response is conditions precedent and staged drawdown. Fund commissioning and refinancing against the asset, then release working capital on licence issuance. That protects the lender without stalling the project, and it forces the question of what happens if the licence takes six months instead of two weeks.

The honest version is the one that gets funded

Deals like this fail more often from presentation than from substance. A pre-revenue borrower presented as an operating business invites the lender to discover the gap themselves, and discovery destroys trust faster than disclosure ever does.

State it plainly: the entity is pre-revenue, the track record sits with the parent, and the thesis rests on tangible asset coverage, parent support, and imminent licensing. A lender who is comfortable with that will engage. One who is not was never going to fund it, and finding out at term sheet stage costs both sides months. If you are structuring or placing a financing of this kind, get in touch.

Get these in your inbox

Choose the updates you would like to receive by email.

Send me*

You can unsubscribe at any time using the link in our emails.

More articles in this category will appear here.

← Back to Market Insights

Working on something in this space?

Discuss it with us